Protect Lakeville Preserving Our Land, Water, Wildlife & Community

Law & Oversight

MEPA

Massachusetts Environmental Policy Act thresholds and the anti-segmentation rule.

60-Second Summary

  • Direct alteration of 25 or more acres is an ENF threshold where MEPA jurisdiction applies; 50 or more acres is an ENF-plus-mandatory-EIR threshold.
  • MEPA jurisdiction generally requires a state Agency Action in addition to the acreage threshold.
  • 301 CMR 11.01's anti-segmentation rule requires the entirety of a project, including likely future expansion, to be considered together.
Confirmed FactRequires Determination

Key Facts

25+ ac
Direct alteration — ENF threshold
Confirmed Fact
50+ ac
Direct alteration — ENF + mandatory EIR
Confirmed Fact

Why This Matters in Lakeville

Massachusetts Environmental Policy Act thresholds and the anti-segmentation rule.

What Is Known

Confirmed Fact

The thresholds, effective January 30, 2026

Under 301 CMR 11.03, direct alteration of 25 or more acres is an ENF threshold where MEPA jurisdiction applies, and direct alteration of 50 or more acres is an ENF-plus-mandatory-EIR threshold, subject to listed exceptions such as approved forest-cutting or farm plans.

MEPA jurisdiction generally requires a state Agency Action — a state permit, financial assistance, land transfer, or state agency project — in addition to meeting the acreage threshold.

Key sources

  1. 301 CMR 11.00 — MEPA regulations, effective Jan. 30, 2026 (25/50-acre thresholds; anti-segmentation rule) — Massachusetts Executive Office of Energy and Environmental Affairs, 2026-01-30
  2. Does my project require MEPA review? (jurisdiction and thresholds) — Mass.gov (live document — verify current version)
View full source library →
Confirmed Fact

Anti-segmentation

301 CMR 11.01 requires the entirety of a project — including likely future expansion — to be considered together, and states that a proponent may not phase or segment a project to evade, defer, or curtail MEPA review.

Key sources

  1. 301 CMR 11.00 — MEPA regulations, effective Jan. 30, 2026 (25/50-acre thresholds; anti-segmentation rule) — Massachusetts Executive Office of Energy and Environmental Affairs, 2026-01-30
View full source library →
Requires Determination

What Has Not Yet Been Established

  • Whether the 565.77-acre parcel size equals the disturbed/altered acreage (it does not, by itself)
  • Which state approvals could create the Agency Action that triggers MEPA jurisdiction
  • Whether the stated earth-removal-to-future-development relationship raises the anti-segmentation question

Related Pages

Sources

Key sources

  1. 301 CMR 11.00 — MEPA regulations, effective Jan. 30, 2026 (25/50-acre thresholds; anti-segmentation rule) — Massachusetts Executive Office of Energy and Environmental Affairs, 2026-01-30
  2. Does my project require MEPA review? (jurisdiction and thresholds) — Mass.gov (live document — verify current version)
View full source library →