Rail Feasibility

Moving material by rail is not simply a routing choice — it requires physical infrastructure, an operating agreement, and a receiving customer. This page lays out what that actually involves.

60-Second Summary

  • The active rail line through Lakeville is owned by the MBTA and carries South Coast Rail passenger service, which the governing framework gives priority over freight movements within defined dispatch windows.
  • Mass Coastal Railroad holds freight operating rights on the corridor under agreement with the MBTA.
  • A rail-served operation at this site would require new infrastructure — at minimum a turnout, siding, and loading track — plus a written service and operating agreement; none of that has been documented publicly for this project.
  • At 100% by rail, 6.45M cubic yards is approximately 8,712,698 tons and 79,207 loaded railcars — see the interactive calculator for adjustable assumptions.
Confirmed FactCalculated ScenarioRequires Determination

Take Action

Help Protect Lakeville

Add your name to the petition asking the Lakeville Select Board to deny and not approve the earth-work permit for the proposed 30 Howland Road earth-removal operation as presently proposed.

3Verified Signatures Requesting Non-Approval
Sign the Petition
80–100
Typical cars per unit train
Confirmed Fact
100–110
Tons per aggregate railcar
Confirmed Fact
24 hrs
Free time before demurrage (Mass Coastal tariff)
Confirmed Fact
0.80–1.00 mi
Approx. siding/staging length for one unit train
Calculated Scenario

Illustrative scenario — not an applicant operating commitment

39,604
Loaded railcars
39,604
Empty car movements
496
Loaded trains
99
Trains/year (5-yr project)

Fixed inputs: total project volume of 6,453,850 cubic yards, 27 ft³ per cubic yard. Bulk density range reflects MassDOT soil design guidance (approx. 99–102 lb/ft³ for loose dry sand); actual on-site material has not been characterized. This calculator assumes rail service is available — see Rail Feasibility for what that would actually require.

What Rail-Served Operation Requires

Confirmed Fact

Ownership and freight rights

The MBTA owns the active rail corridor through Lakeville as part of the South Coast Rail lines transfer completed in 2025, which brought approximately 43 miles of the New Bedford, Fall River, Middleboro, and Watuppa lines under MBTA ownership.

Mass Coastal Railroad holds freight operating rights on lines within this network under agreement with the MBTA, and lists its operating territory publicly.

Confirmed Fact

Passenger priority and dispatch windows

The South Coast Rail Final Supplemental Environmental Impact Report describes passenger service holding operating priority on the shared corridor, with freight movements accommodated within defined dispatch windows around the passenger schedule rather than at any time freight traffic chooses.

This means any new freight volume — including a rail-served aggregate operation — would need to be scheduled around, not alongside, the passenger timetable.

Key sources

  1. South Coast Rail Final Supplemental EIR — passenger priority, freight operating windows, PTC — MassDOT / MBTA
View full source library →
Confirmed Fact

Physical infrastructure a loading operation requires

  • Turnout — the switch connecting a new siding to the main line
  • Siding and staging track — length sized to the unit-train car count (see calculation above)
  • A dedicated loading track separate from through-traffic movements
  • Railcar storage/holding capacity for empty cars awaiting loading and loaded cars awaiting pickup
  • Positive Train Control (PTC) and signal system integration consistent with MBTA/Mass Coastal requirements
  • Aggregate load-out infrastructure: conveyors, hoppers or silos, and a scale for weighing loaded cars
  • Dust suppression at the load-out point
  • Site drainage engineered around the loading and storage area
  • Qualified flagging and inspection procedures for any work adjacent to the active corridor

Key sources

  1. South Coast Rail Final Supplemental EIR — passenger priority, freight operating windows, PTC — MassDOT / MBTA
  2. Mass Coastal Railroad Tariff MC 9100 (2025) — siding acceptance, demurrage, weighing, special train service — Mass Coastal Railroad, 2025
  3. Aggregate, sand and gravel railcar equipment — typical 100–110 ton capacities — CSX Transportation
View full source library →
Confirmed Fact

Agreements and commercial dependencies

A rail-served operation depends on a written operating/service agreement with the railroad, consistent with published tariff terms such as Mass Coastal's Tariff MC 9100 (siding acceptance, demurrage, weighing, and special train service).

It also depends on a receiving end-user — a customer at the far end of the rail movement willing and able to accept the material — since aggregate railcars generally move to a specific buyer, not to an open market.

Key sources

  1. Mass Coastal Railroad Tariff MC 9100 (2025) — siding acceptance, demurrage, weighing, special train service — Mass Coastal Railroad, 2025
View full source library →
Calculated Scenario

Capital cost benchmarks — not a Lakeville-specific estimate

This site does not estimate a specific dollar cost for a Lakeville siding, because no engineering design, scope, or contractor bid for this project has been published. The figures below are unrelated public benchmarks, shown only to illustrate that rail infrastructure of this kind is a substantial capital undertaking, not a minor add-on.

A comparable Massachusetts rail contract (the Berkshire Line project) totaled approximately $7.29 million for 8.7 track-miles plus turnout, crossing, and structure work. A privately funded 25-acre rail transload facility in Texas was estimated at approximately $5.5 million. A federally funded rail transload facility in Virginia received a $25 million RAISE grant in 2025.

None of these benchmarks describes this site, its soil conditions, its required siding length, or its scope of work. They should not be used to infer a specific cost for 30 Howland Road.

Key sources

  1. Berkshire Line rail contract — approx. $7.29M for 8.7 track-miles plus turnout/crossing/structure work — MassDOT / COMMBUYS
  2. Privately funded 25-acre rail transload facility — estimated $5.5M — Texas Department of Licensing & Regulation
  3. RAISE 2025 grant fact sheet — Stafford County rail transload facility, $25M award — U.S. Department of Transportation, 2025
View full source library →
Requires Determination

What Has Not Yet Been Established

  • Whether any siding, turnout, or loading-track design has been submitted to the MBTA or Mass Coastal Railroad
  • Whether a written railroad operating/service agreement exists or is even under negotiation
  • Whether a receiving end-user or customer has been identified
  • What percentage of total volume, if any, the applicant is actually committing to move by rail versus truck
  • Engineering plans for load-out, dust suppression, drainage, and PTC/signal integration

Related Pages

Frequently Asked Questions

Can the material at 30 Howland Road actually be moved by rail?

Physically, yes — an active MBTA-owned rail line with Mass Coastal Railroad freight rights runs through Lakeville. But a rail-served operation is not simply a routing choice — it requires new infrastructure (at minimum a turnout, siding, and loading track), a written operating/service agreement with the railroad, and a receiving end-user willing to accept the material. None of that has been documented publicly for this project.

What infrastructure would be needed to use the railroad at 30 Howland Road?

At minimum: a turnout connecting a new siding to the main line, a siding and staging track sized to the unit-train car count, a dedicated loading track, railcar storage/holding capacity, Positive Train Control and signal integration, aggregate load-out infrastructure (conveyors, hoppers or silos, a scale), dust suppression at the load-out point, and engineered site drainage.

Does South Coast Rail already operate through Lakeville?

Yes. South Coast Rail passenger service, owned and operated by the MBTA, began running through Lakeville in March 2025, using a corridor where the MBTA completed a lines transfer bringing approximately 43 miles of track under its ownership.

Sources

Key sources

  1. South Coast Rail Lines Transfer — approx. 43 miles transferred to MBTA (New Bedford, Fall River, Middleboro, Watuppa lines) — MassDOT Board of Directors, 2025-02-26
  2. South Coast Rail Final Supplemental EIR — passenger priority, freight operating windows, PTC — MassDOT / MBTA
  3. Operating lines and South Coast freight rights — Mass Coastal Railroad
  4. Mass Coastal Railroad Tariff MC 9100 (2025) — siding acceptance, demurrage, weighing, special train service — Mass Coastal Railroad, 2025
  5. Aggregate, sand and gravel railcar equipment — typical 100–110 ton capacities — CSX Transportation
  6. Berkshire Line rail contract — approx. $7.29M for 8.7 track-miles plus turnout/crossing/structure work — MassDOT / COMMBUYS
  7. Privately funded 25-acre rail transload facility — estimated $5.5M — Texas Department of Licensing & Regulation
  8. RAISE 2025 grant fact sheet — Stafford County rail transload facility, $25M award — U.S. Department of Transportation, 2025
  9. South Coast Rail project overview — MBTA ownership and construction status — MBTA (live document — verify current version)
View full source library →